CNIM
COMMISSIONING ENGINEER
June 2013 to June 2014 :
Description : Writing of commissioning procedures on several English projects
- Challenge N°1 : Writing of 30 to 40 Cold Commissioning Procedures 6 to 10 months before commissioning start – delay : 6 to 8 weeks by project
- Consulting of all available documents (PID, Functional Analysis, suppliers’ documentation…)
- Analysis & improvement (when necessary) of available documents
- Writing of procedures
- Internal validation of document before client approval
- -Problems :
- Internal Documents not finished
- Missing of Suppliers’ Documents
- Commissioning not specified into consulting requisitions
- Solutions :
- Use of similar documents on other previous projects
- Standardization of all commissioning procedures to reduce modification between 2 projects
- Participation of commissioning requisition on studying phase
- Analysis & improvement of documents between different projects (in order to avoid to repeat similar errors)
- Modification of technical requisitions to integrate commissioning needs
- Challenge N°2 : realization of 2 commsisioning files
- France : Nesle project
- England : Stafford project
- French project (20 files) :
- No written procedure at the beginning of commissioning, but Expert commissioning engineer in charge
- Large quantity of working documents available
- Very short delay : 3 weeks – 100% job done – working team of 3 people
- English project (100 Files) :
- Written procedure different from the one used on-site, so re-writing of all procedure to have signed & validated documents
- Missing signatures, people in charge gone on other projects
- Technical Documents lost during commissioning
- No traceability of tests done on-site
- 90% job done before end of mission (change on interest from client)