June 2013 to June 2014  :

   Description : Writing of commissioning procedures on several English projects

  • Challenge N°1 : Writing of 30 to 40 Cold Commissioning Procedures 6 to 10 months before commissioning start – delay : 6 to 8 weeks by project
  • Consulting of all available documents (PID, Functional Analysis, suppliers’ documentation…)
  • Analysis & improvement (when necessary) of available documents
  • Writing of procedures
  • Internal validation of document before client approval
  • -Problems :
  • Internal Documents not finished
  • Missing of Suppliers’ Documents
  • Commissioning not specified into consulting requisitions
  • Solutions :
  • Use of similar documents on other previous projects
  • Standardization of all commissioning procedures to reduce modification between 2 projects
  • Participation of commissioning requisition on studying phase
  • Analysis & improvement of documents between different projects (in order to avoid  to repeat similar errors)
  • Modification of technical requisitions to integrate commissioning needs
  • Challenge N°2 : realization of 2 commsisioning files
    • France : Nesle project
    • England : Stafford project

 

  • French project (20 files) :
  • No written procedure at the beginning of commissioning, but Expert commissioning engineer in charge
  • Large quantity of working documents available
  • Very short delay  : 3 weeks – 100% job done – working team of 3 people
  • English project (100 Files) :
  • Written procedure different from the one used on-site, so re-writing of all procedure to have signed & validated documents
  • Missing signatures, people in charge gone on other projects
  • Technical Documents lost during commissioning
  • No traceability of tests done on-site
  • 90% job done before end of mission (change on interest from client)