CLEMESSY SERVICES
PLANNER – SUPERVISOR
March 2019 to June 2019:
Mission: AIR LIQUIDE Pont de Claix – Great Shut Down
Description: Manager Planning – Mechanical / Piping Supervisor
Challenge: to conceive in 7 weeks the planning of the Great Shutdown + to create the Excel File for the follow-up report
Environment: Very short Shut Down, only 3 weeks to perform all the job, including 3 non-working days (Eastern, 1 & 8 May)
- Safety for the teams working on the plant – Co activity
- Working planning preparation
- Joints preparation for
- Safety Valves
- Heat Exchangers
- Follow on the Excel File
Results :
Very good beginning, excellent preparation phase for the team. Specifics procedures for Valves & Safety Valves.
Several Gases Alerts during the shutdown, because of others companies on the VENCOREX Area. Several hours stop each time.
3 / 4 days with Great Winds (between 100 & 120 km/h) without any Leverage.
Finally, all works realized on time or before expected schedule (Valves & Safety Valves 2 to 8 days before schedule according area)