SEGULA
MECHANICAL & PRESSURE VESSEL ENGINEER
January 2018 to February 2018: Mission TOTAL Donges
- : Installation General Engineer, in charge of boiler equipment + other process equipment (pumps, pipes...)
- : to perform in only 5 weeks a job that an outgoing person should done in 3 months with a "dead line" in to February 28 for the entire project.
- : initial codes construction very various, and some old ones, before the arrival of the EC (SNCT / CODAP 90 / ASME) with new notes of calculation according to CODAP 2015 + 2014/68/EU Directive
- Establishment of a standard procedure defining the working methods and principles for cladding operations. (Weld Overlay, Hot/Cold Roll Bonding, Explosion, Weld Cladding...) and Lining
- Drafting of general work procedures on three different workshops,
- Drafting of technical specifications for consultation of making changes on Pressure Vessel Equipment
- Integration of the new European Directive equipment 2014/68/EU in lieu of the 97/23/EC European Directive and of the Decree of 15 March 2000
- Writing piping drafting procedures
- Writing & update of data sheets and document review PID
- Isometrics / TIE Ins review
- : Objectives achieved in due time, all documents were made and approved at the time. Most of the work has been to convince the customer to abandon any idea of the lining and the right methods of cladding depending on the operations to be performed