HOUSE CONSTRUCTION / RETROFIT
December 2015 to February 2016: Renovation rental apartment (52100)
- Function : mastery of work + work
- Challenge : Challenge: transform an apartment built in 1950 in a modern apartment
- Living space : 60 m² - 3 rooms + bathroom + kitchen + WC
- Work to do
- Complete replacement electric installation
- Replacement windows single glazed by window double glazing fitted
- Kitchen Creation American type
- Rehabilitation of soils and paintings
- Bathroom Renovation
February 2010 to present: Renovation House Home (52130)
- Function : Project Management / Site Foreman / « Journeyman »
- Challenge : transform a home built in 1880 in a modern dwelling in retaining its outer stamp. Presence of a historical monument (listed Church) just opposite, so habitable interaction with the monuments of France
- Living area : 120 m² initialy - 300 m² end of roject
- Annexe area : 180 m² initialy – 150 m² end of roject
- Phase 1 – February to June 2010: preliminary Audit & choice of companies
- State audit
- Technical requisitions / consultations / companies choice
- Budget / negotiating with the Bank
- Planning follow up
- Analysis of tenders & equipment provided
- Technical upgrade / ordering
- Phase 2 – Juillet July 2010 to December 2011: main work
- Shell structural & roof
- Civil work
- Outside renovation & painting
- Insulation
- External joinery
- Phase 3 – January 2012 to present : second work
- Outside (garden, access…)
- Electricity, Sanitary, Heating
- woodwork Interior
- Menuiseries intérieures
- bathroom kitchen
August 1998 to December 2009 : Construction House Home (68800)
- Function : Project Management / Site Foreman / « Journeyman »
- Challenge : Construction of a house on slope (15%) wholesale and major interior finish for August 2000
- Living area : 200 m²
- Annexe area : 150 m²
- Phase 1 – August 1998 to December 1999 : preliminary work
- Deforestation, grubbing up hedgerows
- Piped water and electricity construction
- Drafting specifications
- Consultation and choice of providers
- Phase 2 – February 1999 to June 1999: main work
- Civil
- Framing work / roof
- External joinery
- Final water supply, connections gas and electricity, sewer
- Phase 3 – June 1999 to August 2000 : second work phase 1
- Plastering (ceilings, BA13, plaster tiles)
- Electricity,
- Sanitary / heating floor
- Tiles, paintings primary
- Creation kitchen American type, bathroom, shower room
- Phase 4 – September 2000 to December 2009 : second work phase 1 – garden, access
- Decoration inside
- Closets, fireplace,
- Paint finish, wallpaper
- Design attic and basement facilities
- Outside: cabin garden, Garden, self-locking (330 m²), stairs, access
Add a comment